In short
- Give the contractor the heaviest load and the way the slab will be used.
- Calculate cubic yards yourself and check the mix design and reinforcement plan.
- Check runoff and storage rules with state agencies before pouring feed or manure pads.
Figure the job and the use
Concrete for a machinery shop, a feed apron, a manure pad and a silage bunker each calls for something different. Heavy equipment, acids from silage or manure and freezing weather all affect the mix and thickness. Tell the contractor what will sit on the pad, the heaviest load and how the slab will be cleaned. Ask about thickness, reinforcement with rebar or wire mesh, control joints and slope for drainage. A pad that holds water or manure runoff may also trigger environmental rules, so check before you pour.
Quantities and ordering
Concrete is sold by the cubic yard. A simple example: a pad 30 feet by 50 feet at 6 inches thick is 30 times 50 times 0.5, or 750 cubic feet. Divide by 27 and you get about 27.8 cubic yards. Add some extra for uneven subgrade and spillage, often a few percent, and ask the supplier how they recommend ordering. Short loads can carry extra fees, so ask. Do not rely on a rough guess when you can measure. Your contractor should give you the quantity calculation in writing.
Base, forms and reinforcement
A good slab sits on good ground. Ask about site preparation: stripping topsoil, compacting the subgrade and placing a gravel base. Soft spots can crack a slab, so ask how the contractor will handle them. Ask about forms, rebar size and spacing, mesh, chairs to hold steel at the right height and expansion joints. Reinforcement helps control cracks but does not prevent them. Control joints guide where cracks happen. Ask who places and finishes the concrete and how long they have done this work.
Mix, weather and curing
Ask for the mix design: strength rating, air entrainment for freeze and thaw areas and the slump. Strength needs depend on use, and heavy equipment and silage call for higher ratings than light storage. Adding water on the job weakens concrete, so watch for it. Hot, cold and windy weather change how concrete sets. Ask how the crew will protect it in bad weather and how long it will cure. Curing, which means keeping the slab moist or covered, makes a big difference. Do not drive heavy equipment onto a new pad too early. Follow the supplier and Extension guidance on timing.
Permits, runoff and safety
Feed pads, manure pads and silage bunkers may fall under state rules on runoff and storage. Contact your state department of agriculture or environmental agency, your NRCS office and your Extension office before you build. Cost share programs may exist for some structures, but they often require approval before work begins. Check for underground utilities with the locating service. Ask the contractor about insurance and workers' compensation. Silage pads and bunker walls also need design for the pressure of packed feed, so use an engineered plan.
Bids, contract and inspection
Get written bids that list size, thickness, reinforcement, mix, base prep, forming, finishing, sealing, cleanup and warranty. Compare line by line. Ask for references and look at slabs a few years old for cracking, scaling and drainage problems. Pay in stages tied to progress. After the pour, inspect for surface defects and check slope with water. Hairline cracks are common, but wide cracks, heaving and crumbling surfaces are not. Keep tickets from the concrete supplier, since they record mix and time. Ask the contractor whether they use a sealer or curing compound and when it goes on. Ask how the crew will handle a sudden shower or a pump breakdown mid pour, and who decides to stop if the trucks run late. A job that runs into the evening often gets rushed finishing. Confirm the days the pour crew and the finishers will be on site, and that someone from the company stays until the slab is covered and protected, so you are not left watching a drying surface alone.